Optimizing SMD Machine Efficiency Without New Investment

Sponsor

Head of Operations

Location

Nordrhein-Westfalen, Germany

Electronics, Sensors

Optimizing SMD Machine Efficiency Without New Investment
Team

Production, Production Planning & Control

Key Performance Indicators

Productivity, Lead Time, Quality

Impact

Lead Time: -3 days;
WIP Reduction: €135k;
Productivity Gain: €200k;
Output Increase: 60/min → 110M/year

The Challenge

The client was considering purchasing a new SMD machine due to the low OEE and insufficient performance.

The Solution

OEE analysis identified unused potential. Optimized changeover time, grouped products, installed fixed tooling, and improved material supply.

The Result

Avoided unnecessary machine investment; Increased efficiency and machine output